What are the notification procedures for issuance of new building permits/alteration permits?
For new construction building permits, a plaque issued thru the Division of Permits must be posted prior to any work commencing on the site after a building permit is issued. […]
Am I required to be onsite during an inspection?
You are not required to be onsite unless contacted by an inspector. However, a designated person shall be on site during a final inspection.
How long does it take to get an inspection?
Once an inspection is requested, no work shall be done beyond the point of that inspection until it has been met satisfactory as completed by Department of Permits inspector. If […]
What time is building construction allowed? Can work be done on weekends?
Building construction can occur during the hours of 7:00 AM to 10:00 PM, Monday- thru Saturday, including holidays. Any work done before or after these hours must not exceed the […]
Where do I find out who owns the fence’?· Which side determines ownership, flat side or the support side?
This is a civil matter and not in the Department of Planning and Natural Resources jurisdiction. A survey may often be required to determine ownership. Generally, fence ownership is 50/50 […]
What is the process to appeal the issuance· of a building permit?
Contact the Board of Land Use Appeals. You have 30 calendar days from the day of issuance to file an appeal through The Department of Justice.
What is the permit fee to file for a building permit or to submit plans?
The permit fee depends on the project valuation. You may contact the Department of Planning and Natural Resources – Division of Permits at dpnr.vi.gov or (340)774-3320 or (340)773-1082 for a […]
How do I find out the status of my building permit application?
You may contact the Department of Planning and Natural Resources – Division of Permits, General Information Line at (340)774-3320 or (340)773-1082.